Hello all,

I can see that HOMER shows the hourly energy production of components in the Simulation Results of a project. I was wondering if HOMER can provide this information in smaller intervals, such as every 5 minutes. Any suggestions would be appreciated.

Thank you!

ReplyQuote
Posted : July 10, 2017 10:26 am
(@dhiwaakar)
Illustrious HOMER Admin

Hi Minnie,

 

You can change the minutes per timestep from 60 minutes to a smaller resolution. This can be done through: Project -> Optimization -> Minutes per timestep. Hope this helps.

 

 

Best Regards,

Dhiwaakar Rajasekaran