 A real PV project consists of components in their ’bill of materials’, such as lightning arrestor, charge controller, cables, ancillaries etc.a
In homer, this is limited to 3-4 components namely PV, Battery, converter, Grid.
For my thesis, I want to model the existing real case, into homer and analyse the technical and economical results. This would provide a comparison between the true performance of the project, and the predictions.
Is there a way to add the real costs of a project into homer?

ReplyQuote
Posted : October 22, 2017 11:53 am
(@dhiwaakar)
Illustrious HOMER Admin

Hi Anguvika,

 

Any additional costs can be added to system fixed capital or O&M costs. You can find more information about these costs in our help documentation. Below are the links to the documentation.

https://www.homerenergy.com/support/docs/3.10/system_fixed_capital_cost.html

https://www.homerenergy.com/support/docs/3.10/system_fixed_operations_and_maintenace_om_cost.html

 

Best,

ReplyQuote